Remaining is negative or the project shows over 100%
It is arithmetic, not a bug — here is what to do about it.
Steps
- Earned passed the contract total, almost always because quantities ran past bid on a few items.
- If the owner pays overruns at the unit price, nothing needs changing; the application bills the measured quantity.
- If the overrun is a change, add the change order. The contract rises and the percentage settles back under 100.